Electrical System Maintenance Activity Tower 1 & 2
-
January 25, 2023
-
PMO
-
CN-2023-006
In line with our continuous effort to ensure electrical
system reliability, please be advised that we will be
conducting a system maintenance activity from
February 6 to 21, 2023. In line with this activity,
there will be a power interruption on the schedule below:
Date |
Time |
February 6, 2023, 9AM-6PM
|
Tower 1, 6th – 12th Floor
|
February 7, 2023, 9AM-6PM
|
Tower 1, 15th – 20th Floor
|
February 8, 2023, 9AM-6PM
|
Tower 1, 21st – 26th Floor
|
February 9, 2023, 9AM-6PM
|
Tower 1, 27th – 31st Floor
|
February 10, 2023, 9AM-6PM
|
Tower 1, 32nd – 35th Floor
|
February 11, 2023, 9AM-6PM
|
Tower 1, 36th – 39th Floor
|
February 13, 2023, 9AM-6PM
|
Tower 1, 40th – 43rd Floor
|
February 14, 2023, 9AM-6PM
|
Tower 2, 6th – 12th Floor
|
February 15, 2023, 9AM-6PM
|
Tower 2, 15th – 20th Floor
|
February 16, 2023, 9AM-6PM
|
Tower 2, 21st – 26th Floor
|
February 17, 2023, 9AM-6PM
|
Tower 2, 27th – 31st Floor
|
February 18, 2023, 9AM-6PM
|
Tower 2, 32nd – 35th Floor
|
February 20, 2023, 9AM-6PM
|
Tower 2, 36th – 39th Floor
|
February 21, 2023, 9AM-6PM
|
Tower 2, 40th – 43rd Floor
|
During the power interruption period, emergency power
will be available for use. The purpose of this activity
is to ensure functionality of our busduct system to
avoid unnecessary power interruption in the future.
Should you need further clarification in this regard,
please do not hesitate to call our office at telephone
number (02) 8400-3395 or email us at sun.admin@greenmist.ph
or pmo@sunresidences.ph.
Pest Control Schedule - January 2023
-
January 5, 2023
-
PMO
-
CN-2023-002
Please be guided on the common area pest control service for the month of January:
Date |
Time |
January 13, 2023
|
9:00 AM - 5:00 PM
|
January 27, 2023
|
9:00 AM - 5:00 PM
|
For those who wish to avail the pest control services inside their
respective units, there will be a PhP 175.00 fee which you
can settle directly with the pest control service provider.
You may coordinate with our property engineers for the scheduling.
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarification, you may contact the Property Management Office at
(02) 8400-3395 or send us an email at sun.admin@greenmist.ph or
pmo@sunresidences.ph.
Quarterly Preventive Maintenance Of Generator
-
December 14, 2022
-
PMO
-
CN-2022-103
In line with our continuous effort to maintain our Electrical System and Equipment,
please be advised that we will be conducting the Quarterly Preventive Maintenance of
our Generators and Automatic Transfer Switch (ATS) Simulation where there will be
an expected power fluctuation due to transferring of Normal Power to Emergency
Power and vice versa.
The purpose of the activity is to proactively check the functionality of
the Generator and ATS in case of emergency.
Kindly see below the schedule for reference.
Date |
Time |
December 23, 2022
(10:00 AM to 11:00 AM)
|
All Floors (Tower 1)
|
ATS Simulation and Load Testing
|
December 23, 2022
(11:00 AM to 12:00 PM)
|
All Floors (Tower 1)
|
ATS Simulation and Load Testing
|
For queries and clarification, you may contact the Property Management Office at
(02) 8400-3395, (02) 7718-4364 or send us an email at sun.admin@greenmist.ph or
pmo@sunresidences.ph.
We apologize for the inconvenience and hope for your kind understanding.
Thank you for your usual cooperation.
Pest Control Schedule - October 2022
-
October 3, 2022
-
PMO
-
CN-2022-080
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on October 14 and 28, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364, (02) 8400-3395 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Tower 1 – ATS (Automatic Transfer Switch) Troubleshooting
-
October 3, 2022
-
PMO
-
CN-2022-079
In line with the conducted quarterly preventive maintenance
of Generator last September 27, 2022, please be advised
that we will be re-conducting ATS (Automatic Transfer Switch)
simulation at Tower 1 only on October 6, 2022 at 10:00 AM to 12:00 PM
to further troubleshoot the control as we observe delay on the
transition when transferring power from Normal to Emergency, and vice versa.
Kindly expect power fluctuation on the common area during the activity.
Residential Units will not be affected on the power interruption.
All Elevators on Tower 1 and the Low Rise Elevator at Tower 2 will be
temporarily shut down before transferring of power supply to avoid mantrap
and malfunction on the units.
For queries and clarification, you may contact the Property Management
Office at (02) 8400-3395, (02) 7718-4364 or send us an email at
sun.admin@greenmist.ph or pmo@sunresidences.ph.
We apologize for the inconvenience and hope for your kind understanding.
Thank you for your usual cooperation.
Quarterly Preventive Maintenance of Generator
-
September 16, 2022
-
PMO
-
CN-2022-075
In line with our continuous effort to maintain our
Electrical System and Equipment, please be advised
that we will be conducting the Quarterly Preventive
Maintenance of our Generators and Automatic Transfer
Switch (ATS) Simulation where there will be an expected
power fluctuation due to transferring of Normal Power to
Emergency Power and, vice versa.
The purpose of the activity is to proactively check the
functionality of the Generator and ATS in case of emergency.
Kindly see below the schedule for reference:
Date and Time |
Area |
Activity |
September 27, 2022 (10:00 AM to 11:00 AM)
|
All Floors (Tower 1)
|
ATS Simulation and Load Testing
|
September 27, 2022 (11:00 AM to 12:00 PM)
|
All Floors (Tower 2)
|
ATS Simulation and Load Testing
|
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364, (02) 8400-3395 or send us an email at sun.admin@greenmist.ph or
pmo@sunresidences.ph.
Pest Control Schedule - September 2022
-
August 26, 2022
-
PMO
-
CN-2022-070
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on September 9 and 23, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364, (02) 8400-3395 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Pest Control Schedule - August 2022
-
July 28, 2022
-
PMO
-
CN-2022-066
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on August 12 and 26, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364, (02) 8668-8124 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Annual Preventive Maintenance of Pressure Relief Valve (PRV)
-
July 16, 2022
-
PMO
-
CN-2022-063
Please be informed that Eastman Industrial Supply Inc.,
the commissioned contractor by the Condominium Corporation will be conducting an Annual Preventive
Maintenance of Pressure Relief Valve (PRV) on July 21 - 22, 2022. This is to maintain
our equipment in good condition and to ensure its reliability. Below is the schedule and
the affected areas during the activity.
Date
|
Time
|
Activity
|
Affected Areas
|
July 21, 2022
|
9:00 AM - 5:00 PM
|
Preventive Maintenance and
Cleaning of PRVs
|
6th floor to 43rd floor (Tower 1)
|
July 22, 2022
|
9:00 AM - 5:00 PM
|
Preventive Maintenance and
Cleaning of PRVs
|
6th floor to 43rd floor (Tower 2)
|
NOTE: During the PRV Preventive Maintenance, water discoloration and intermittent
low pressure to no water supply may be experienced.
|
Ahead of schedule, the Property Management Office is advising affected areas/units to
store enough water to avoid inconvenience during the duration of activities.
For further clarifications, you may contact the Property Management Office at (02) 7718-
4364, (02) 8668-8124 or send us an email at sun.admin@greenmist.ph or
pmo@sunresidences.ph.
Pest Control Schedule - July 2022
-
June 29, 2022
-
PMO
-
CN-2022-058
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on July 8 and 22, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364, (02) 8668-8124 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Quarterly Preventive Maintenance of Generator
-
June 8, 2022
-
PMO
-
CN-2022-050
In line with our continuous effort to maintain our Electrical System and Equipment, please be
advised that we will be conducting our Quarterly Preventive Maintenance of our Generators and
Automatic Transfer Switch (ATS) Simulation where there will be an expected power fluctuation
due to the transfer of Normal Power to Emergency Power and vice versa.
The purpose of the activity is to proactively check the functionality of the Generator and ATS in
case of emergency.
Kindly see below the schedule for reference:
Date and Time |
Area |
Activity |
June 20, 2022 (10:00 AM to
10:15 AM)
|
All Floors (Tower 1)
|
ATS Simulation and Load Testing
|
June 20, 2022 (10:15 AM to
10:30 AM)
|
All Floors (Tower 2)
|
ATS Simulation and Load Testing
|
For queries and clarification, you may contact the Property Management Office at
(02) 8668-8124, (02) 7713-4364 or send us an email at sun.admin@greenmist.ph
or pmo@sunresidences.ph.
We apologize for the inconvenience and hope for your kind understanding.
Thank you for your usual cooperation.
Pest Control Schedule - June 2022
-
June 8, 2022
-
PMO
-
CN-2022-049
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on June 10 and 24, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364, (02) 8668-8124 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Intercom Rehabilitation Schedule
-
June 2, 2022
-
PMO
-
CN-2022-048
Please be advised that Valiant Advance System and Devices Corporation, our accredited
contractor, will now start the Intercom Rehabilitation of main system (part of the
special assessment project) beginning today,
June 2, 2022, from 9:00 AM to 5:00 PM on Mondays to Fridays.
The scope of the activity will include the checking and troubleshooting of the intercom
inside the unit, below schedule for your information:
Tower 1 |
Date |
Floor |
Date |
Floor |
Date |
Floor |
June 6, 2022
|
6th - 7th
|
June 13, 2022
|
20th - 21st
|
June 20, 2022
|
32nd - 33rd
|
June 7, 2022
|
8th - 9th
|
June 14, 2022
|
22nd - 23rd
|
June 21, 2022
|
34th - 35th
|
June 8, 2022
|
10th - 11th
|
June 15, 2022
|
24th - 25th
|
June 22, 2022
|
36th - 37th
|
June 9, 2022
|
12th - 15th
|
June 16, 2022
|
26th - 27th
|
June 23, 2022
|
38th - 39th
|
June 10, 2022
|
16th - 17th
|
June 17, 2022
|
28th - 29th
|
June 24, 2022
|
40th - 41st
|
June 11, 2022
|
18th - 19th
|
June 18, 2022
|
30th - 31st
|
June 25, 2022
|
42nd - 43rd
|
Tower 2 |
Date |
Floor |
Date |
Floor |
Date |
Floor |
June 27, 2022
|
6th - 7th
|
July 4, 2022
|
20th - 21st
|
July 11, 2022
|
32nd - 33rd
|
June 28, 2022
|
8th - 9th
|
July 5, 2022
|
22nd - 23rd
|
July 12, 2022
|
34th - 35th
|
June 29, 2022
|
10th - 11th
|
July 6, 2022
|
24th - 25th
|
July 13, 2022
|
36th - 37th
|
June 30, 2022
|
12th - 15th
|
July 7, 2022
|
26th - 27th
|
July 14, 2022
|
38th - 39th
|
July 1, 2022
|
16th - 17th
|
July 8, 2022
|
28th - 29th
|
July 15, 2022
|
40th - 41st
|
July 2, 2022
|
18th - 19th
|
July 9, 2022
|
30th - 31st
|
July 16, 2022
|
42nd - 43rd
|
With this, kindly allow technicians from the contractor to access your unit. They will be
wearing their company uniforms with IDs together with complete PPEs. Rest assured,
that their activities will be closely monitored by our CCTV Operator, roving security guards
and engineering maintenance team.
Procedure in troubleshooting is that: SRCC staff, together with Valiant technicians will
knock first before accessing your unit, they will inspect the intercom line and unit for
troubleshooting and this will last for about twenty (20) minutes.
If the intercom unit is found defective and deemed for replacement or repair, this will be
under the Unit Owner's account following the below provision in the Master Deed:
Article III Declaration of Restriction, Section 6 Maintenance, Repairs
Alterations, 6.1 to wit:
"All maintenance and repair work on any of the units other
than the maintenance and repair of any of the Common Areas or facilities
contained therein shall be for the account of the Owner. Each unit shall be
responsible for all the damages caused to any other Unit and/or to any portion of
the building resulting from its failure to effect the required maintenance and repair
of his Unit. Each Unit shall also be obliged to promptly report in writing to the
Condominium Corporation any defect or need for repair in any of the Common
Areas found in or within the vicinity of his Unit."
The cost of the device for replacement is PhP 7,587.20 / unit (VAT inclusive), while the
repair is PhP 4.334.00 / unit (VAT inclusive) and will be billed on the following month or
during the release of monthly Statement of Account.
For further clarifications, you may contact the Property Management Office at (02) 8668-8124,
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Pest Control Schedule - May 2022
-
April 25, 2022
-
PMO
-
CN-2022-038
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on May 13 and 27, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Pest Control Schedule - April 2022
-
March 29, 2022
-
PMO
-
CN-2022-031
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on April 8 and 22, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Annual Preventive Maintenance of Electrical
System and Meralco Transformers
-
March 22, 2022
-
PMO
-
CN-2022-028
Please be advised that our electrical contractor, Static Power Philippines Inc.,
will be conducting Annual Preventive Maintenance for Electrical System.
With this, Sun Residences will be experiencing a power interruption and will be
supplied with emergency power during the adivity.
Please see schedule of power interruption below:
Area
|
Date/Time
|
Emergency Power Supply
|
Residential Units (Tower 1 & 2)
|
March 16, 2022 (7:00 AM - 6:00 PM)
|
Residential units:
- 1 outlet, 200W (near kitchen area)
- 1 light (living area)
Note: Limited to a maximum of 6amp load capacity only per unit
|
Common Areas (Tower 1 & 2)
|
Common Areas
- 100% (hallways, elevators, amenities, etc.)
|
|
You may refer to the photo for the operation of the Manual Transfer Switch (MTS) for the
transfer of Normal Power (Meralco) to Emergency Power (Generator), and vice versa.
- In case of brownout, switch OFF Normal Breaker (Blue) and switch ON
Emergency Breaker (Black).
- When Normal Power (Meralco) resumes, switch OFF Emergency Breaker (Black) and
switch ON Normal Breaker (Blue)
|
Kindly take note that the
Emergency Power Supply is limited only and not intended to fully supply power inside
the Residential Units
. Avoid overloading that may cause power outage which may affect other units that are
connected to the Emergency System.
For queries and clarification, you may contact PMO at (02) 7718-4364, (02) 8668-8124 or send us an email at
sun.admin@greenmist.ph or pmo@sunresidences.ph.
Quarterly Preventive Maintenance of Generator
-
March 5, 2022
-
PMO
-
CN-2022-025
In line with our continuous effort to maintain our Electrical System and Equipment, please be
advised that we will be conducting the Quarterly Preventive Maintenance of our Generators and
Automatic Transfer Switch (ATS) Simulation where there will be an expected power fluctuation
due to transferring of Normal Power to Emergency Power and, vice versa.
The purpose of the activity is to proactively check the functionality of the Generator and ATS in
case of emergency.
Kindly see below the schedule for reference:
Date and Time
|
Area
|
Activity
|
March 9, 2022
(10:00 AM to 11:00 AM)
|
All Floors (Tower 1)
|
ATS Simulation and Load Testing
|
March 9, 2022
(11:00 AM to 12:00 PM)
|
All Floors (Tower 2)
|
ATS Simulation and Load Testing
|
For queries and clarifications, you may contact the Property Management Office at
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
We apologize for the inconvenience and hope for your kind understanding. Thank you for your
usual cooperation.
Pest Control Schedule - March 2022
-
March 10, 2022
-
PMO
-
CN-2022-019
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on March 11 and 25, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Pest Control Schedule - February 2022
-
February 10, 2022
-
PMO
-
CN-2022-019
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on February 11 and 25, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Unit Maintenance Reminder
-
January 24, 2022
-
PMO
-
CN-2022-010
This is to remind all unit owners and residents of the following maintenance works/activities which should
be conducted regularly to avoid unnecessary inconvenience(s) and/or damage(s) to other units and common
areas. You may get the service of outside contractors to do some of the maintenance works or you may opt
to do them on yoür own.
Solid Waste Managenent/Garbage Disposal
-
All wastes should be placed in a garbage bag and thrown into the bin provided inside
the garbage room.
-
Do not leave your garbage bags outside your unit or along the hallway.
-
Recyclable wastes like PET bottles, boxes and the likes should left on the floor inside the
garbage room.
NOTE:We are enjoining everyone to dispose of all your wastes properly. Kindy refrain from flushing
insoluble materials thru your kitchen sink and toilet bowls. Incidents of sewer backflows and leaks
were traced to be caused by flushed items like shirts, underwear, cigarette butts, etc. Please
understand that once's negligence will lead to bigger problems and may affect the whole community later on.
Grease Traps
All sink drains have provided with grease traps underneath. Accumulation of grease/food
waste can be avoided by installing a strainer in your kitchen sink. It is recommended to clean the
grease trap once or twice a month to avoid over flowing and clogging of pipes. Avoid using enzymes,
acids or solvents when cleaning your grease traps as this may affect the good bacteria/activated
sludge being maintained in our Sewage Tratrnent Plant (STP).
Sink Cabinet
Check and verify all sink cabinets if they are still in good condition. Make sure that
counter, sink and splash boards are intact to prevent water leaks affecting unit(s) below.
Flexible Hose
This can be found connected with your faucets, heaters, and water closets. Weekly checking for
cracks and minor leaks is to be done.
Range Hoods
Monthly cleaning of range hood filter is recommended to be done.
Air-Conditioning Units
Residents shall keep such device in good appearance and working condition and shall not allow
leak/condensation to accumulate or make noise which disturbs other residents of the building. Air
conditioning drains must be regularly cleaned/de-clogged by the unit owner or resident to prevent
clogging and water backflows. Any damage(s) caused by leaks and backflows to residential units
or areas shall be repaired by the unit owner, resident or tenant concerned.
Balcony Railings and Fittings
Balcony railings need attention due to their exposure to weather cycles. Periodic inspection and
preventive repairs are needed to avoid deterioration and corrosion. Balcony railings can be
constructed from a variety of different materials including aluminum, steel, cast iron and glass. Glass
should be periodically inspected for cracks while steel and cast iron railings including fittings should
be scraped, primed and painted every few years or at least once a year depending on the weather
conditions. Powder coated materials should be pressure washed using filtered water at low pressure
setting to avoid damaging finish, cleaned with either a soft cloth or a brush using a solution of
mild soap and warm filtered water and applied with a light coating of high-grade non-abrasive car
wax to increase the service life of the coated surface.
Lastly, please be reminded that our House Rules Sections 2.4.1.1, 2.4.1.2, and 2.4.1.20 provide that
"each unit owner, tenant, and/or resident is obliged to keep and maintain his/her unit in good and
sanitary condition and in a manner that shall not prejudice other unit owners, tenants, and/or
residents. The unit owner, tenant, and/or resident shall also be solely responsible for
compensating the affected unit owners, tenants, and/or residents for damages caused by
the negligence of the former and/or the persons for whom he/she is responsible for,
whether visitors, employees, agents, contractors or dependents."
For further clarifications, you may contact the Property Management Office at
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Pest Control Schedule - January 2022
-
January 10, 2022
-
PMO
-
CN-2022-007
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on January 14 and 28, 2022.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For queries and clarification, you may contact the Property Management Office at
(02) 7718-4364 or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Quarterly Preventive Maintenance of Generator
-
September 2, 2021
-
PMO
-
CN-2021-084
In line with our continuous effort to maintain our Electrical System and Equipment, please be advised
that we will be conducting the Quarterly Preventive Maintenance of our Generators and ATS (Automatic
Transfer Switch) Simulation where there will be an expected power fluctuation due to transferring of
Normal Power to Emergency Power and, vice versa.
The purpose of the activity is to proactively check the functionality of our Generator and ATS in case of
emergency.
Kindly see below the schedule of power interruption for reference:
Date and Time |
Area |
Activity |
September 9, 2021 (10:00 AM to 11:00 AM)
|
All Floors (Tower 1)
|
ATS Simulation
|
September 9, 2021 (11:00 AM to 12:00 PM)
|
All Floors (Tower 2)
|
ATS Simulation
|
For any queries or clarifications, you may contact the Property Management Office at
(02) 7750-7168, (02) 8668-8124 or send us an email
at sun.admin@greenmist.ph or pmo@sunresidences.ph.
We apologize for the inconvenience and hope for your kind understanding. Thank you for your usual
cooperation.
Pest Control Schedule - September 2021
-
September 1, 2021
-
PMO
-
CN-2021-082
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on September 10 (Friday) and 24 (Friday), 2021.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Pest Control Schedule - August 2021
-
August 9, 2021
-
PMO
-
CN-2021-068
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on August 13 (Friday) and 27 (Friday), 2021.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Reiteration of Circular 2021-058
-
July 22, 2021
-
PMO
-
CN-2021-059
In line with the Circular No. 2021-058 with Subject: Power Interruption in Common Areas –
Tower 1 and Podium schedule on July 23, 2021, please be advised that the PMO – Admin
Office and the Passenger Elevator – Low Rise Tower 2 will also be affected by the Power
Interruption.
See below the schedule of the power interruption.
Time
|
Activity
|
Between 9:00 AM to 11:00 AM
|
Temporary termination of wires from Generator to directly
connect to the Common Area Panel of Tower 1 for Power
Supply
|
Between 1:00 PM to 4:00 PM
|
Re-termination of wires to restore all connections
|
Transactions at the PMO will be temporarily unavailable and Passenger Elevators – Low Rise of
Tower 2 will not be operational during the abovementioned schedule. Our fire exits will be
opened for easy access. The entire activity and area will be strictly monitored by our Security
and Engineering Departments.
Residential units will not be affected during the power interruption.
Should you need further clarification in this regard, please do not hesitate to call our office at
(02) 7750-7168 or (02) 8668-8124.
We apologize for the inconvenience and hope for your kind understanding. Thank you for your
usual cooperation.
Power Interruption In Common Areas – Tower 1 and Podium
-
July 16, 2021
-
PMO
-
CN-2021-058
In line with our continuous effort to maintain our Electrical System, we will be having a
scheduled power interruption in the Common Area and Podium of Tower 1 on July 23, 2021
to perform the replacement of the Emergency Breaker of the Automatic Transfer Switch (ATS)
at the Generator Room. This activity is to ensure that our Emergency Power Supply from the
Generator will be readily available in case of power interruption from Meralco.
See below the schedule of the power interruption in the common area.
Time
|
Activity
|
Between 9:00 AM to 11:00 AM
|
Temporary termination of wires from Generator to directly
connect to the Common Area Panel for Power Supply
|
Between 1:00 PM to 4:00 PM
|
Temporary termination of wires from Generator to directly
connect to the Common Area Panel for Power Supply
|
Please be advised that all of the elevators and lightings in the common area of Tower 1 will not
be operational during the power shutdown. Our fire exits will also be opened for easy access.
The entire activity and area will be strictly monitored by our Security and Engineering
Department.
Residential units will not be affected during the power interruption.
Should you need further clarification in this regard, please do not hesitate to call our office at
(02) 7750-7168 or (02) 8668-8124.
We apologize for the inconvenience and hope for your kind understanding. Thank you for your
usual cooperation.
Emergency Power Interruption for Tower 1
-
June 16, 2021
-
PMO
-
CN-2021-050
In line with the recent power interruption happen today, we will be conducting Emergency
Simulation Testing for our Generator at Tower 1. This is to verify the cause of power
interruption in Tower 1 during absence of Normal Power (supply coming from Meralco).
During the said activity, we will be experiencing 15 minutes Power Interruption for Tower
1 on June 16, 2021 (Wednesday) between 2:00 PM to 5:00 PM.
We apologize for the inconvenience and hope for your kind understanding.
For any queries or clarifications, you may contact the Property Management Office at
(02) 7750-7168 or send us an email
at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Thank you for your usual cooperation.
Quarterly Preventive Maintenance of Generator
-
June 11, 2021
-
PMO
-
CN-2021-048
In line with our continuous effort to maintain our Electrical System and Equipment, please be advised
that we will be conducting the Quarterly Preventive Maintenance of our Generators and ATS (Automatic
Transfer Switch) Simulation where there will be an expected power fluctuation due to transferring of
Normal Power to Emergency Power and, vice versa.
The purpose of the activity is to proactively check the functionality of our Generator and ATS in case of
emergency.
Kindly see below the schedule of power interruption for reference:
Date and Time |
Area |
Activity |
June 15, 2021 (10:00am to 10:15am)
|
All Floors (Tower 1)
|
ATS Simulation
|
June 15, 2021 (10:15am to 10:30am)
|
All Floors (Tower 2)
|
ATS Simulation
|
For any queries or clarifications, you may contact the Property Management Office at
(02) 7750-7168 or send us an email
at sun.admin@greenmist.ph or pmo@sunresidences.ph.
We apologize for the inconvenience and hope for your kind understanding. Thank you for your usual
cooperation.
Pest Control Schedule - June 2021
-
June 3, 2021
-
PMO
-
CN-2021-044
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on June 11 (Friday) and 25 (Friday), 2021.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Flood Testing At Tower 1 Roofdeck
-
June 1, 2021
-
PMO
-
CN-2021-043
In line with our Waterproofing activity at Tower 1 Roof deck, please be advised that
Megastruct Inc. will start to conduct
Flood Testing from June 5, 2021 to June 10, 2021.
The purpose of this activity is to ensure the workmanship and efficiency of the
waterproofing. With this, we encourage our residents at tie 43rd Floor to coordinate
immediately to our Security Guards and Maintenance staff once leak has manifested
inside your units during tie activity.
For any queries or clarifications, you may contact the Property Management Office at
(02) 7750-7168 or send us an email
at sun.admin@greenmist.ph or pmo@sunresidences.ph.
FDAS Corrective Maintenance Schedule
-
March 2, 2021
-
PMO
-
CN-2021-013
We would like to inform you of our updated Preventive and Corrective Maintenance schedule of our
Fire Detection Alarm System (FDAS) in Tower 1 which we started last March 8, 2021 and was halted
during the implementation of MECQ.
Please be advised that the commissioned contractor Vanler
Construction And Trading Services (Vanler) by SRCC will resume
the said project on May 26, 2021.
Refer to the table below for the complete details.
Date |
Floor |
May 26, 2021
|
10th - 11th
|
May 27, 2021
|
8th - 9th
|
May 28 2021
|
6th - 7th
|
Kindly allow technicians from Vanler Construction and Trading Services to
access your unit. They will be wearing their company uniforms with ID together with complete
PPE's (face mask and face shield). Rest assured that their activities will be closely monitored by
our CCTV Operator and roving security guards.
Procedures in troubleshooting of smoke detectors line will be as follows: Vanler Technicians will
knock first and access your unit, remove the detector, troubleshoot the line, clean smoke
detector at electrical room and reinstall it. The troubleshooting work will only last for about ten
(10) minutes.
If the smoke detector inside unit is found defective and deemed for replacement, this will be
under the Unit Owner's account following the below provision in the Master Deed:
Article Ill Declaration of Restriction, Section 6 Maintenance, Repairs Alterations,
6.1 to wit:
"All maintenance and repair work on any of the Units other than the
maintenance and repair of any of the Common Areas or facilities contained therein shall
be for the account of the Owner. Each unit shall be responsible for all the damages
caused to any other Unit and/or to any pottion of the building resulting from its failure to
effect the required maintenance and repair of his Unit. Each Unit shall also be obliged to
promptly report in writing to the Condominium Corporation any defect or need for repair
in any of the Common Areas found in or within the vicinity of his Unit."
The cost of the device is PhP 5,040.00/unit (VAT inclusive) and will be billed on the following
month or during the release of monthly Statement of Account.
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Flood Testing at Tower 1 Roof-deck
-
May 10, 2021
-
PMO
-
CN-2021-034
In line with our Waterproofing activity at Tower 2 roof-deck, please be advised that
Megastruct Inc. will start to conduct
Flood Testing from May 20 (Thursday) to May 29 (Saturday), 2021.
The purpose of this activity is to ensure the workmanship and efficiency of the
waterproofing. With this, we encourage our residents at the 43rd Floor to coordinate
immediately to our Security Guards and Maintenance staff once leak has manifested inside
your units during the activity.
Should you have any queries regarding this matter, please feel free to coordinate with the
Property Management Office.
For queries or clarifications, you may contact the Property Management Office at
(02) 7750-7168 or send us an email
at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Thank you for your usual cooperation.
Globe's LTE Activation & Testing
-
May 3, 2021
-
PMO
-
CN-2021-032
In line with Globe's LTE Activation & Testing activity at Tower 1 and Tower 2, please be advised
that Globe's 2G/3G and LTE Services will have at least 4 hours' downtime on both
Towers on May 5, 2021 from 12:00 PM up to 4:00 AM.
Their activity aims to upgrade the current technologies inside the premises to continuously
provide best in class services to their subscribers who demand a faster and more reliable
Telecommunications service.
For queries and clarification, you may contact the Property Management Office at (02) 7750-7168
or send us an email at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Pest Control Schedule - May 2021
-
April 28, 2021
-
PMO
-
CN-2021-029
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on May 14 (Friday) and 21 (Friday), 2021.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Flood Testing at Tower 2 Roof-deck
-
April 21, 2021
-
PMO
-
CN-2021-027
In line with our Waterproofing activity at Tower 2 roof-deck, please be advised that
Megastruct Inc. will start to conduct
Flood Testing from May 3 (Monday) to May 12 (Wednesday), 2021.
The purpose of this activity is to ensure the workmanship and efficiency of the
waterproofing. With this, we encourage our residents at the 43rd Floor to coordinate
immediately to our Security Guards and Maintenance staff once leak has manifested inside
your units during the activity.
Should you have any queries regarding this matter, please feel free to coordinate with the
Property Management Office.
For queries and darification, you may contact the Property Management Office at
(02) 7750-7168 or send us an email
at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Thank you for your usual cooperation.
Roof-deck Re-Waterproofing (Tower 1)
-
April 10, 2021
-
PMO
-
CN-2021-023
Please be advised that Megastruct Inc., will begin our re-waterproofing project on
April 15, 2021 at Tower 1 roof-deck. This is to prevent water leaks and
possible damages during rainy seasons.
Kindly expect noisy works from 8:00 AM to 5:00 PM for the duration of the activity as there will be grinding works for the
surface preparation of the area. Residents of the 43/F are encouraged to coordinate immediately to our
Security Guards and/or Maintenance staff if leak has manifested inside your units during the activity.
Should you have any queries regarding this matter, please feel free to coordinate with the Property Management
Ofice.
For queries and darification, you may contact the Property Management Office at (02) 7750-7168 or send us an email
at sun.admin@greenmist.ph or pmo@sunresidences.ph.
Thank you for your usual cooperation.
Scheduled Power Interruption
-
March 16, 2021
-
PMO
-
CN-2021-017
In line with our continuous effort to maintain our Electrical System, please be advised
that we will be having a scheduled power interruption to conduct the maintenance of
Meralco Transformers, Generator Emission Testing, Bus Duct and Plug-In Breaker audit.
These are to ensure the system's condition, prevent unwanted downtime and any
untoward incident that may arise.
Kindly see below the schedules for reference:
Date and Time |
Area |
Activity |
March 26, 2021 (8:00 AM to 5:00 PM)
|
All Floors
(Tower 1 and 2)
|
PM of Transformer and
Generator Emission Testing
|
April 5, 2021 (9:00 AM to 6:00 PM)
|
15 to 20 Floor and 40 to 43 Floor
(Tower 1)
|
Busduct and Plug-In
Breaker Audit
|
April 5, 2021 (9:00 AM to 6:00 PM)
|
15 to 20 Floor and 40 to 43 Floor
(Tower 1)
|
Busduct and Plug-In
Breaker Audit
|
April 6, 2021 (9:00 AM to 6:00 PM)
|
21 to 26 Floor and 36 to 39 Floor
(Tower 1)
|
Busduct and Plug-In
Breaker Audit
|
April 7, 2021 (9:00 AM to 6:00 PM)
|
27 to 31 Floor and 32 to 35 Floor
(Tower 1)
|
Busduct and Plug-In
Breaker Audit
|
April 8, 2021 (9:00 AM to 6:00 PM)
|
6 to 12 Floor
(Tower 1)
|
Busduct and Plug-In
Breaker Audit
|
April 12, 2021 (9:00 AM to 6:00 PM)
|
15 to 20 Floor and 40 to 43 Floor
(Tower 2)
|
Busduct and Plug-In
Breaker Audit
|
April 13, 2021 (9:00 AM to 6:00 PM)
|
21 to 26 Floor and 36 to 39 Floor
(Tower 2)
|
Busduct and Plug-In
Breaker Audit
|
April 14, 2021 (9:00 AM to 6:00 PM)
|
27 to 31 Floor and 32 to 35 Floor
(Tower 2)
|
Busduct and Plug-In
Breaker Audit
|
April 15, 2021 (9:00 AM to 6:00 PM)
|
6 to 12 Floor
(Tower 2)
|
Busduct and Plug-In
Breaker Audit
|
During the activity, affected floors will have Emergency Power supply only. Kindly note
that Emergency Power is limited to 1-outlet and 1-lighting only to avoid overloading.
While for the other floors, power supply will be normal.
Should you need further clarification in this regard, please do not hesitate to call our
office at telephone numbers (02) 7750-7168, (02) 8668-8124.
We apologize for the inconvenience and hope for your kind understanding. Thank you
for your usual cooperation.
Pest Control Schedule - March 2021
-
March 5, 2021
-
PMO
-
CN-2021-014
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on March 12 (Friday) and 26 (Friday), 2021.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
FDAS Corrective Maintenance Schedule
-
March 2, 2021
-
PMO
-
CN-2021-013
In line with our ongoing Preventive and Corrective Maintenance of our Fire Detection Alarm
System (FDAS), please be informed that we will be conducting
Free Cleaning and
Troubleshooting of Smoke Detectors line
on residential units and hallways on
March 8 to 30, 2021 from 8:00 AM - 12:00 PM, 1:00 PM - 5:00 PM at Tower 1.
Tower 1 |
Date |
Floor |
Date |
Floor |
Date |
Floor |
March 8, 2021
|
42nd - 43rd
|
March 16, 2021
|
30th - 31st
|
March 23, 2021
|
18th - 19th
|
March 9, 2021
|
40th - 41st
|
March 17, 2021
|
28th - 29th
|
March 24, 2021
|
16th - 17th
|
March 10, 2021
|
38th - 39th
|
March 18, 2021
|
26th - 27th
|
March 25, 2021
|
12th - 15th
|
March 11, 2021
|
36th - 37th
|
March 19, 2021
|
24th - 25th
|
March 26, 2021
|
10th - 11th
|
March 12, 2021
|
34th - 35th
|
March 22, 2021
|
22nd - 23rd
|
March 29, 2021
|
8th - 9th
|
March 15, 2021
|
32nd - 33rd
|
March 23, 2021
|
20th - 21st
|
March 30, 2021
|
6th - 7th
|
Kindly allow technicians from Vanler Construction and Trading Services to
access your unit. They will be wearing their company uniforms with ID together with complete
PPE's (face mask and face shield). Rest assured that their activities will be closely monitored by
our CCTV Operator and roving security guards.
Procedures in troubleshooting of smoke detectors line will be as follows: Vanler Technicians will
knock first and access your unit, remove the detector, troubleshoot the line, clean smoke
detector at electrical room and reinstall it. The troubleshooting work will only last for about ten
(10) minutes.
If the smoke detector inside unit is found defective and deemed for replacement, this will be
under the Unit Owner's account following the below provision in the Master Deed:
Article Ill Declaration of Restriction, Section 6 Maintenance, Repairs Alterations,
6.1 to wit:
"All maintenance and repair work on any of the Units other than the
maintenance and repair of any of the Common Areas or facilities contained therein shall
be for the account of the Owner. Each unit shall be responsible for all the damages
caused to any other Unit and/or to any pottion of the building resulting from its failure to
effect the required maintenance and repair of his Unit. Each Unit shall also be obliged to
promptly report in writing to the Condominium Corporation any defect or need for repair
in any of the Common Areas found in or within the vicinity of his Unit."
The cost of the device is PhP 5,040.00/unit (VAT inclusive) and will be billed on the following
month or during the release of monthly Statement of Account.
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Pest Control Schedule - February 2021
-
February 9, 2021
-
PMO
-
CN-2021-008
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on February 12 (Friday) and 26 (Friday), 2021.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Pest Control Schedule - January 2021
-
January 6, 2021
-
PMO
-
CN-2021-001
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on January 15 (Friday) and 29 (Friday), 2021.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Pest Control Schedule - December 2020
-
December 7, 2020
-
PMO
-
CN-2020-115
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on December 11 and 29, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Pre-Thermal Scanning of EE Rooms
-
December 7, 2020
-
PMO
-
CN-2020-114
In line with Circular No: 2020-110 - The Annual PM of our Electrical System and Meralco Transformers, please be
advised that our Electrial Contractor will also be conducting a Pre-Thermal Scanning of our EE Rooms on
December 7 - 8, 2020 from 6:00 PM to 12:00 AM.
-
December 7, 2020 - Tower 1
-
December 8, 2020 - Tower 2
This will be an activity conducted per floor and the residents will be experiencing a split second power fluctuation
during the course of the activity. No power interruption will be experienced.
Rest assured that the Engineering Team will be monitoring and assisting the Electrical Contractor while they are
conducting this activity.
Should you need further clarification in this regard, please do not hesitate to call our office at telephone numbers
(02) 7750-7168, (02) 8668-8124.
We apologize for the inconvenience and hope for your kind understanding. Thank you for your usual cooperation.
Annual Preventive Maintenance of Electrical
System and Meralco Transformers
-
November 28, 2020
-
PMO
-
CN-2020-110
Please be advised that our electrical contractor
will be conducting
Annual Preventive Maintenance for
Electrical System
on December 14 - 15, 2020.
With this, residents will be experiencing a power interruption
and will be supplied with emergency power during the course
of the activity.
Kindly see below schedule of power interruption:
Area
|
Date/Time
|
Emergency Power Supply
|
Residential units & common areas
|
December 14, 2020 - Tower 1 (7:00 AM - 7:00 PM)
December 15, 2020 - Tower 2 (7:00 AM - 7:00 PM)
|
Residential units:
- 1 outlet (near kitchen area)
- 1 light (living area)
Note: Limited to a maximum of 6amp load capacity only per unit
|
Common areas:
- 100% (hallways, elevators, amenities, etc.)
|
|
You may refer to the photo for the operation of the Manual Transfer Switch (MTS) for the
transfer of Normal Power (Meralco) to Emergency Power (Generator), and vice versa.
- In case of brownout, switch OFF Normal Breaker (Blue) and switch ON
Emergency Breaker (Black).
- When Normal Power (Meralco) resumes, switch OFF Emergency Breaker (Black) and
switch ON Normal Breaker (Blue)
|
Kindly take note that the Emergency Power Supply is limited only and not intended to fully supply power inside
the Residential Units. Avoid overloading that may cause power outage which may affect other units that are
connected to the Emergency System.
Should you need further clarification in this regard, please do not hesitate to call our office at telephone number
(02) 7750-7168, (02) 8668-8124.
We apologize for the inconvenience and hope for your kind understanding. Thank you for your usual cooperation
Elevator Load Testing
-
November 17, 2020
-
PMO
-
CN-2020-107
Please be informed that Load Testing Activity of our elevators
will be conducted on November 19, 2020 to November 24, 2020 (except on Weekends). With this, operations of our elevators
will be affected during the given schedule. However, please note that this activity will be done
sequentially to minimize the interruption of our operations.
Kindly see schedule details below.
Date |
Time |
Elevator |
November 19, 2020 (Thursday)
|
10:00 AM - 6:00 PM
|
High Rise Tower 2 (One elevator at a time)
|
November 20, 2020 (Friday)
|
10:00 AM - 6:00 PM
|
Low Rise Tower 2 (One elevator at a time)
|
November 23, 2020 (Monday)
|
10:00 AM - 6:00 PM
|
Low Rise Tower 1 (One elevator at a time)
|
November 24, 2020 (Tuesday)
|
10:00 AM - 6:00 PM
|
High Rise Tower 1 (One elevator at a time)
|
Should you need further clarification in this regard, please do not hesitate to call our office at
telephone numbers (02) 7750-7168, (02) 8668-8124.
Pest Control Schedule - November 2020
-
November 4, 2020
-
PMO
-
CN-2020-101
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on November 5, 12, 19 and 26, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Passenger Elevators 3 and 8 Downtime
-
October 20, 2020
-
PMO
-
CN-2020-096
We would like to inform our residents that the below elevators are in need of a major part replacement as
assessed by Hyundai:
Tower |
Elevator |
Tower 1
|
Passenger Elevator 3
(High Rise — Low Zone)
|
Tower 2
|
Passenger Elevator 8
(High Rise - Low Zone)
|
The replacement part will be coming from overseas, hence, requiring a longer lead time.
Rest assured that the PMO is closely monitoring with our Service Provider for the immediate repair.
Should you need further clarification in this regard, please do not hesitate to call our office at telephone
number (02) 7750-7168 and (02) 8668-8124.
Pest Control Schedule - October 2020
-
October 8, 2020
-
PMO
-
CN-2020-091
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on October 9, 20 and 23, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Elevator - Main Wire Rope Replacement Project #5
-
September 8, 2020
-
PMO
-
CN-2020-082
Please be advised that we are to conduct the replacement of our Main Wire Rope and repair of Deflector
Sheave for Passenger Elevator 6 - High Rise of Tower 2 on the below schedule:
Tower |
Elevator |
Date |
Tower 2
|
Passenger Elevator 6
High Rise - High Zone
|
September 15 - 26, 2020
|
Should you need further clarification in this regard, please do not hesitate to
call our office at telephone number (02) 7750-7168.
We apologize for the inconvenience and hope for your kind understanding.
Pest Control Schedule - September 2020
-
September 8, 2020
-
PMO
-
CN-2020-081
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on September 11 and 25, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Pest Control Schedule - August 2020
-
August 11, 2020
-
PMO
-
CN-2020-076
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on August 14 and 28, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Elevator - Main Wire Rope Replacement Project (4 of 4)
-
August 8, 2020
-
PMO
-
CN-2020-073
Please be advised that we are to conduct the replacement of our Main Wire Rope and
repair of Deflector Sheave for Passenger Elevator 5 of Tower 2 on the below schedule
Tower
|
Elevator
|
Date
|
Tower 2
|
Passenger Elevator 5
(High Rise - High Zone)
|
August 12 - 24, 2020
|
Should you need further clarification in this regard, please do not hesitate to call our office at
telephone number (02) 7750-7168.
We apologize for the inconvenience and hope for your kind understanding.
Pest Control Schedule - July 2020
-
July 10, 2020
-
PMO
-
CN-2020-065
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on July 10 and 24, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office at telephone
number (02) 7750-7168.
Pest Control Schedule - June 2020
-
June 9, 2020
-
PMO
-
CN-2020-058
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00 AM - 5:00 PM on June 10 and 26, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest Control Schedule - March 2020
Please be advised that GEPESTCON CO., our pest control
contractor will conduct their monthly pest control
services for the common area from
9:00AM - 5:00PM on March 13 and 27, 2020.
Scope of the activity will include the following control
measures for common area treatment:
Name |
Position |
Mosquitoes
|
Residual spraying, thermal
ULV misting, Mist blowing
(water-based) at parking
area.
|
Flies
|
Residual spraying, thermal
ULV misting.
|
Cockroaches
|
Residual spraying.
|
Pest control services inside the unit is every
Tuesday and Saturday, if you wish to avail the service
there will be a PhP 250.00 fee which you can settle
directly to GEPESTCON. You can coordinate with
the Property Management Office for the scheduling.
For clarifications, please do not hesitate to contact the Property Management Office
at +63 (2) 7750-7168.
Elevator - Main Wire Rope Replacement Project (2 of 4)
-
February 16, 2020
-
PMO
-
CN-2020-016
Please be advised that we are to conduct the replacement of our Main Wire Rope and
repair of Deflector Sheave for Passenger Elevator 2 of Tower 1 on the below schedule
Tower
|
Elevator
|
Date
|
Tower 1
|
Passenger Elevator 2
(High Rise - High Zone)
|
February 20 - March 3, 2020
|
Should you need further clarification in this regard, please do not hesitate to call our office at
telephone number +63 (2) 7750-7168.
We apologize for the inconvenience and hope for your kind understanding.
Generator Sets Emission Testing
-
February 4, 2020
-
PMO
-
CN-2020-010
In relation to the compliance and application for renewal of our
Permit to Operate (PTO), Aeronics Incorporated will be conducting
an air emission test on February 7, 2020 (Friday).
During this activity, we will operate the generator sets serving
the common area and residential units of both towers. Residents will
experience power interruption for four (4) hours and will be
supplied with emergency power during the course of the activity.
Kindly see below schedule of power interruption:
Area
|
Time
|
Emergency Power Supply
|
Common Area
|
1:00PM to 5:00PM
|
100% to all common areas
(Hallways, Elevators, Anenities, etc.)
|
Residential Units
|
1:00PM to 5:00PM
|
1 outlet (Refrigerator) and 1 light
(Living Area)
|
Should you need any assistance, please contact our Property
Management Office at +63 (2) 7750-7168.
Thank you for your kind understanding.
Elevator - Main Wire Rope Replacement Project (1 of 4)
-
January 14, 2020
-
PMO
-
CN-2020-003
Please be advised that we are to conduct the replacement of our Main Wire Rope and
repair of Deflector Sheave for Passenger Elevator 1 of Tower 1 on the below schedule
Tower
|
Elevator
|
Date
|
Tower 1
|
Passenger Elevator 1
(High Rise - High Zone)
|
January 24 - February 4, 2020
|
Should you need further clarification in this regard, please do not hesitate to call our office at
telephone number +63 (2) 7750-7168.
We apologize for the inconvenience and hope for your kind understanding.
Annual Preventive Maintenance of Electrical
System and Meralco Transformers
-
October 29, 2019
-
PMO
-
CN-2019-071
Please be advised that our electrical contractor
will be conducting
Annual Preventive Maintenance for
Electrical System
on November 5-6, 2019.
With this, residents will be experiencing a power interruption
and will be supplied with emergency power during the course
of the activity.
Kindly see below schedule of power interruption:
Area
|
Date/Time
|
Emergency Power Supply
|
Residential units & common areas
|
November 5 & 6, 2019 (09:00 AM - 6:00 PM)
|
2 outlets (bedroom and refrigerator)
with 6amp maximum load capacity only
and 1 light (living area)
|
100% to all common areas (Hallways,
Elevators, Amenities, Etc.)
|
For clarifications, please do not hesitate to contact
the Property Management Office at +63 (2) 7750-7168.
Preventive Maintenance of Fire Detection and Alarm System
-
October 28, 2019
-
PMO
-
CN-2019-071
Please be informed that on
October 28-31, 2019
from 9:00AM to 5:00PM
, Vanler, our service provider will
conduct its
Annual Preventive Maintenance Check-up of
the Fire Detection and Alarm System
of the building.
During this activity, unexpected alarms in selected floors can
be activated. Kindly disregard these alarms as they are connected
to the troubleshooting and rectification process.
Counting on your kindest understanding and usual cooperation.
For clarifications, please do not hesitate to contact
the Property Management Office at +63 (2) 7750-7168.
Bladder Tank Replacement
-
September 18, 2019
-
PMO
-
CN-2019-061
Please be informed that Bladder Tank Replacement for
our Water System at 39/F to 43/F of Tower 1 and Tower 2 will be
conducted on September 24 and October 1, 2019 respectively. With this,
we will have water interruption on the said dates from
1:00PM to 5:00PM.
Should you need further clarification in this regard, please
do not hesitate to call our office at +63 (2) 750-7168.
We apologize for any inconvenience this may cause you
and we hope for your understanding.
Intercommunication Rehabilitation Activity
-
September 14, 2019
-
PMO
-
CN-2019-063
Please let this letter serve as our request to access
your unit for the above mentioned subject.
Our technical maintenance staff namely
Kimbo Oliveros,
Anthony Malabarbas, Jhapet Alipao and Angelito Mahinay
are the authorized representatives from the Property
Management Office to conduct the inspection. They will be
presenting this letter and wearing complete
uniform and ID for identification purposes.
Should you need further clarification in this regard, please
do not hesitate to call our office at +63 (2) 750-7168.
We apologize for any inconvenience this may cause you
and we hope for your understanding.
Main Wire Rope Replacement for Service Elevators
-
August 23, 2019
-
PMO
-
CN-2019-058
Please be advised that we are to conduct the replacement
of our Main Wire Rope for both Service Elevators and
repair of Deflector Sheave for Service Elevator 1 of
Tower 1 on the below schedule:
Building
|
Elevator
|
Date
|
Tower 2
|
Service Elevator 2
|
August 30 - September 6, 2019
|
Tower 1
|
Service Elevator 1
|
September 9 - September 21, 2019
|
With this, all food deliveries will be allowed up to
the 6/F Lobby only for us to minimize the foot
traffic during the activity. Furniture and appliance
delivery, move-in and move-out for Tower 1 and Tower 2
will use the High Rise PE 1 and PE 5 respectively.
Should you need further clarification in this regard,
please do not hesitate to contact the Property Management
Office at +63 (2) 750-7168.
Repair of Electrical System at Tower 2
To completely address the electrical issue encountered in
Tower 2 last September 2018, please see timeline and schedule
of power interruptions in residential units given by our
commissioned electrical contractor for the whole duration of this repair.
Floor
|
Date
|
Time
|
January 24, 25 & 28
|
6th Floor to 12th Floor
|
8:00AM – 6:00PM
|
January 29 & 30
|
15th Floor to 20th Floor
|
8:00AM – 6:00PM
|
January 31 & February 1
|
21st Floor to 26th Floor
|
8:00AM – 6:00PM
|
February 4
|
27th Floor to 31st Floor
|
8:00AM – 6:00PM
|
February 6
|
32nd Floor to 35th Floor
|
8:00AM – 6:00PM
|
February 7
|
36th Floor to 39th Floor
|
8:00AM – 6:00PM
|
February 8
|
40th Floor to 43rd Floor
|
8:00AM – 6:00PM
|
Should you need further clarification in this regard,
please do not hesitate to call our office at +63 (2) 917-7195.
Power Interruption Schedule
Sun Residences Condominium Corp will conduct
Annual Preventive Maintenance of Electrical System
in Tower 1 and Tower 2
on
August 13, 2018 (Monday)
from 9:00AM to 5:00PM
. During this test, may we
request for your cooperation to report at Property
Management Office if there is no emergency power
provision in your unit or for any related concern.
For your reference, each unit is allotted with the
following emergency load:
Unit Type
|
Convenience Outlet
|
Lighting
|
Studio
|
(1) C.O. for refrigerator
|
(1) Lighting outlet
|
1 bedroom with balcony
|
(1) C.O. for refrigerator
|
(1) Lighting outlet
|
2 bedroom with balcony
|
(1) C.O. for refrigerator
|
(1) Lighting outlet
|
Should you have any question or need further
clarification in this regard, please do not
hesitate to call our office at telephone number
+63 (2) 668-8124
Power Interruption Schedule
Sun Residences Condominium Corp will conduct Annual
Thermal Scanning and visual check of our Electrical System,
and MERALCO meter center per floor on
July 24 to 25, 2018
from 9:00AM - 5:00PM
.
Please refer to the schedule below:
Date
|
Building
|
July 24, 2018
|
Tower 1
|
July 25, 2018
|
Tower 2
|
Please expect intermittent power interruption for
the entire duration of this maintenance activity.
We are requesting for your understanding and
cooperation.
Should you have any question or need further clarification
in this regard, please do not hesitate to call our office at
telephone number +63 (2) 668-8124.
Shutdown of Elevator Power Supply at Tower 1
In line with our ongoing Repair of Damaged Riser of
Electrical Line at Tower 1, please be advised that
our accredited contractor PHASES Electrical Contractor Corp.
will conduct reconnection of permanent power supply for
elevators and overhead tank booster pumps. Our passenger
and service elevators will be temporarily unavailable on
July 24, 2018 from 12:00AM– 4:00AM.
Should you have any question or need further clarification
in this regard, please do not hesitate to call our office at
telephone number +63 (2) 668-8124.
12/F Tower 2 E.E. Room
Around 6:30AM today, we experienced a power blackout
due to tripped electrical circuit breaker at 12/F of Tower 2.
Property Management Office technical team inspected and
troubleshoot the said concern and it was found out that
circuit breaker was damaged.
We have now contacted the contractors of the Condominium
Corporation to restore the power supply of all 12/F Tower 2 units.
Activity will need approximately 4-6 hours since it will be
dismantling and replacement of defective circuit breaker.
Affected floors will be 6/F to 12/F of Tower 2.
We truly apologize for the inconvenience.
Power Interruption Schedule
Sun Residences Condominium Corp will conduct
Annual Preventive Maintenance of Electrical System
and Preventive Maintenance of Transformer in
Tower 1 and Tower 2
on
June 1, 2018 (Wednesday)
from 9:00AM to 5:00PM
. During this test, may we
request for your cooperation to report at Property
Management Office if there is no emergency power
provision in your unit or for any related concern.
For your reference, each unit is allotted with the
following emergency load:
Unit Type
|
Convenience Outlet
|
Lighting
|
Studio
|
(1) C.O. for refrigerator
|
(1) Lighting outlet
|
1 bedroom with balcony
|
(1) C.O. for refrigerator
|
(1) Lighting outlet
|
2 bedroom with balcony
|
(1) C.O. for refrigerator
|
(1) Lighting outlet
|
Should you have any question or need further
clarification in this regard, please do not
hesitate to call our office at telephone number
+63 (2) 668-8124
Power Interruption Schedule
Sun Residences Condominium Corp will conduct
Annual Thermal Scanning and visual check of
our Electrical System, and MERALCO meter center
per floor on May 24 to 25, 2018.
Please refer to the schedule below:
Date
|
Building
|
May 24, 2018
|
Tower 1
|
May 25, 2018
|
Tower 2
|
Please expect intermittent power interruption for
the entire duration of this maintenance activity.
We are requesting for your understanding and
cooperation.
Should you have any question or need further clarification
in this regard, please do not hesitate to call our office at
telephone number +63 (2) 668-8124.
FDAS Rehabilitation Schedule
Please be informed that we will be conducting
Rehabilitation of all Fire Alarm Control Panels
and Smoke Detectors on specific residential hallways
from
January 30, 2018 to February 28, 2018,
9:00AM-12:00PM | 1:00PM-6:00PM
.
(All days except Sundays and Holidays).
Our accredited contractor, E-Connect Trading and Electrical
Services will facilitate this troubleshooting. They will be
wearing their company uniforms with ID. Rest assured that
their activities will be closely monitored by our CCTV
Operator and roving security guards.
Procedures in troubleshooting the Fire Alarm Control Panel
and smoke detectors will be as follows. E-Connect Technicians
will energize affected panels. Common Area will experience
erratic activation of alarms and sounders
(depending on fault of specific panel will receive).
Please be guided accordingly. Should you have any question
or need further clarification in this regard, please do not
hesitate to call our office at telephone number
+63 (2) 516-5052.
Intercom Troubleshooting and Repair Schedule
Please be informed that we will be conducting a
Troubleshooting and Repair of all Intercom
units from
September 18, 2017 to October 14,
9:00AM-12:00PM, 1:00PM-6:00PM
(All days except Sundays and Holidays).
Kindly allow the technicians from JEES contractor to
access your respective units. They will be wearing
their company uniform and ID. Rest assured that their
activities will be closely monitored by our CCTV
Operators and roving security guards.
We enjoin all residents’ full cooperation and participation
in this regard to expedite the completion of this project.
Should you have any question or need further clarifications
on this matter, please do not hesitate to call our office at
+63 (2) 516-5052.
Pest Control Schedule
Please find hereunder the schedule of general pest control
activities in all our common areas including residential floor
hallways and schedule for tenants for May 2017 up to April 2018:
Schedule For Common Area |
Schedule For Tenants (For PhP 250.00 Per Unit During Given Dates) |
May 12 & 26, 2017
|
May 5, 12, 19 & 26, 2017
|
June 9 & 23, 2017
|
June 2, 9, 16 & 23, 2017
|
July 14 & 28, 2017
|
July 7, 14, 21 & 28, 2017
|
August 11 & 25, 2017
|
August 4, 11, 18 & 25, 2017
|
September 8 & 22, 2017
|
September 1, 8, 15 & 22, 2017
|
October 13 & 27, 2017
|
October 6, 13, 20 & 27, 2017
|
November 10 & 24, 2017
|
November 3, 10, 17 & 24, 2017
|
December 8 & 22, 2017
|
December 1, 8, 15 & 22, 2017
|
January 12 & 26, 2018
|
January 5, 12, 19 & 26, 2018
|
February 9 & 23, 2018
|
February 2, 9, 16 & 23, 2018
|
March 9 & 23, 2018
|
March 2, 9, 16 & 23, 2018
|
April 13 & 27, 2018
|
April 6, 13, 20 & 27, 2018
|
The following treatment will be conducted:
spraying,
misting, rodent control and water-based fogging
.
Given this, kindly make necessary adjustments and observe
the following precautionary measures during the pest control.
-
Food should be removed/tightly covered or placed
inside the cabinets and refrigerators.
-
All exposed personal belongings,
accessories, and the like should be covered with
plastics or newspapers.
- Close all main unit doors during the treatment.
Unit owners who would want to avail the services like
misting and spraying inside the unit may directly
contact the personnel assigned on the aforesaid
dates or may call the following telephone numbers:
+63 (2) 245-7200, +63 (2) 332-7139, +63 (905) 301-7710.
We are requesting your full cooperation on this.
Please be guided accordingly.
FDAS Rehabilitation Schedule
Please be informed that we will be conducting Free Cleaning
of all Smoke Detectors inside units and all residential hallways
from May 22 to June 19, 2017, 9:00AM - 12:00PM and 1:00PM - 6:00PM.
(All days except Sundays and Holidays).
Kindly allow technicians from E-Connect Trading and Electrical Services
to access your unit. They will be wearing their company uniforms with ID.
Rest assured that their activities will be closely monitored by our
CCTV Operator and roving security guards.
Procedures in cleaning the smoke detectors will be as follows.
E-Connect Technicians will knock first and access your unit,
remove the detector, clean it at the electrical room and
reinstall it. The cleaning work will only last for about
five (5) minutes to ten (10) minutes.
Tower 1 |
Date |
43rd to 41st Floor
|
Monday, May 22, 2017
|
40th to 38th Floor
|
Tuesday, May 23, 2017
|
37th to 35th Floor
|
Wednesday, May 24, 2017
|
34th to 32nd Floor
|
Thursday, May 25, 2017
|
31st to 29th Floor
|
Friday, May 26, 2017
|
28th to 26th Floor
|
Saturday, May 27, 2017
|
25th to 23rd Floor
|
Monday, May 29, 2017
|
22nd to 20th Floor
|
Tuesday, May 30, 2017
|
19th to 17th Floor
|
Wednesday, May 31, 2017
|
16th to 12th Floor
|
Thursday, June 1, 2017
|
11th to 9th Floor
|
Friday, June 2, 2017
|
8th to 6th Floor
|
Saturday, June 3, 2017
|
Tower 2 |
Date |
43rd to 41st Floor
|
Monday, June 5, 2017
|
40th to 38th Floor
|
Tuesday, June 6, 2017
|
37th to 35th Floor
|
Wednesday, June 7, 2017
|
34th to 32nd Floor
|
Thursday, June 8, 2017
|
31st to 29th Floor
|
Friday, June 9, 2017
|
28th to 26th Floor
|
Saturday, June 10, 2017
|
25th to 23rd Floor
|
Tuesday, June 13, 2017
|
22nd to 20th Floor
|
Wednesday, June 14, 2017
|
19th to 17th Floor
|
Thursday, June 15, 2017
|
16th to 12th Floor
|
Friday, June 16, 2017
|
11th to 9th Floor
|
Saturday, June 17, 2017
|
8th to 6th Floor
|
Monday, June 19, 2017
|
Please be guided accordingly. Should you have any question or
need further clarification in this regard, please do not
hesitate to call our office at telephone number +63 (2) 516-5052.
Power Interruption Schedule
Please be informed that MERALCO and Property Management Office's (PMO) contractor
will conduct a general cleaning and preventive maintenance
activity of our Electrical System on April 19, 2017 (Wednesday),
which requires an Eight (8) hour Power Interruption from
9:00AM to 5:00PM.
The purpose of this activity is to check and ensure that
SRCC’s equipment is well maintained and to improve the reliability
of our facilities.
Emergency Power will be available during the power interruption.
For the residents, emergency power will be available ONLY on the following:
-
One ceiling lighting fixture (for 1 Bedroom and Studio Type Unit)
-
Two ceiling lighting fixture (for 2 Bedroom Unit)
-
One power outlet assigned to the refrigerator
Kindly report to the PMO or reception
lobbies if any of these items have no electric power supply
during the said power interruption.
Please be guided accordingly. Should you have any question or
need further clarification in this regard, please do not
hesitate to call PMO at +63 (2) 516-5052.
Water Interruption Schedule
Please be advised that there will be a Water Interruption
on April 19, 2017 (Wednesday) from 9:00AM to 12:00PM.
Maynilad, our water service provider will be replacing the
current 75mm diameter water meter with the same size.
This activity is due to the Maynilad management –
initiated program to establish record data for all large meters.
It is also part of the regular meter monitoring and replacement
covered by MWSI Policy No. CS–301-98.
All residents are enjoined to collect sufficient water to supply
your needs during the interruption period. We are requesting
your full cooperation on this.
Please be guided accordingly. Should you have any question or
need further clarification in this regard, please do not
hesitate to call PMO at +63 (2) 516-5052.
Generator Set Load Testing
Please be informed that DYNAMIC M will be conducting
Load Testing of our Generator Sets on
February
23, 2017 (Thursday), from 10:00AM to 11:00AM
.
In this regard, there will be a Power Interruption during
the said activity, but Emergency Power (Generator) will be
activated. Elevators and lightings at all common areas
will be functional. For Residential Units, only
emergency - supplied outlet and lightings will be available.
We are requesting your full cooperation and forbearance
in this regard. Should you have further queries and
clarifications, feel free to call the Property
Management Office at +63 (2) 516-5052 or email us at
pmo@sunresidences.ph.
Tower 1 High Rise Elevators Zoning Scheme
Following the success of the Passenger High Rise
Elevator Zoning Scheme in Tower 2 of Sun Residences
last November 2016, we are pleased to announce that
Tower 1 High Rise Elevators will be under the same
Segmentation Scheme starting on
March 1, 2017 (Wednesday).
Listed below is the floor distribution of each
elevator car in every zone.
Zone |
Elevator |
Floors |
Low
|
3 & 4
|
7th – 25th
|
High
|
1 & 2
|
26th – 43rd
|
Common Stops
|
1, 2, 3 & 4
|
3rd, 5th & 6th
|
We are requesting your full cooperation and
forbearance in this regard. Should you have
further queries and clarifications, feel free to
call the Property Management Office at +63 (2) 516-5052
or email us at pmo@sunresidences.ph.
Water Interruption
Please be informed that Maynilad will conduct a
maintenance activity in M. Cuenco and D. Tuazon
streets of Brgy. Sta. Teresita on
January 15, 2017 (Sunday) to January 16, 2017 (Monday),
which will require a
six (6) hour Water Interruption
between 10:00PM and 4:00AM
. All residents are enjoined to collect sufficient
water to supply your needs during the interruption
period.
We are requesting your full cooperation on this.
Please be guided accordingly.
Should you have any question or need further
clarification, please do not hesitate to call PMO
at +63 (2) 516-5052.
Pest Control Schedule
Please find hereunder the schedule of general pest
control activities in all our common areas including
residential floor hallways.
Schedule |
Time |
2nd and 4th Friday of the Month
|
9:00AM onwards
|
The following treatment will be conducted:
spraying, misting, rodent control and
water-based fogging
.
Given this, kindly make necessary adjustments and
observe the following precautionary measures during
the pest control:
-
Food should be removed/tightly covered or placed
inside cabinets or refrigerators.
-
All exposed personal belongings, accessories,
and the like should be-covered with plastics
or newspapers.
-
Close all main unit doors during the treatment.
Unit owners who would want to avail the services
like misting and spraying inside the unit may directly
contact the personnel assigned on the aforesaid dates
or may call the following numbers: +63 (2) 245-7200,
+63 (2) 332-7139, +63 (905) 301-7710.